|
CHAPTER 4
PERFORMANCE AND OBSERVED BEHAVIOR OF FIELD INSTRUMENTATION
Back
to Table of Contents
The excavation for the Chicago and State subway renovation
project consisted of two areas of excavation. The primary
excavation area was west of the Warde School, along State
Street. This portion of the project involved constructing
a mezzanine section atop the subway tunnel and making the
subway handicap accessible by adding escalators and elevators. Figure
4-1 presents the subway renovation structural plan and
includes the numbering scheme for the secant piles. The figure
also shows the locations of the inclinometers with respect
to the excavation.
The excavation area west of the Warde School
was approximately 40 m long and about 24 m wide. At the
center of the west
side excavation area, the excavation was advanced to the
top of the subway tunnel. The top of the subway tunnel
was about 6.2 m below the ground surface (elevation -1.9
m CCD).
Along the sides of the west excavation area, on either
side of the tunnel, the excavation was advanced to a depth
of
12.2 m (elevation -7.9 m CCD) everywhere along the length
of the tunnel except at the locations of the escalators.
At the escalator locations, the excavation was advanced
to a depth of 13.7 m (elevation -9.4 m CCD).
The secondary
excavation was located on the north side of the Warde School,
along Chicago Avenue. The purpose of this
excavation activity was to add new stairs and an escalator
to the existing station. The secondary excavation area
was approximately 24 m long and 7 m wide. The excavation
was
advanced to a depth of 8.2 m (elevation -4 m CCD) at this
location.
Although the excavation activities were relatively
uniform as the project progressed from the south end to
north end
along State Street, different deformation behavior of the
ground was noted between the east and west sides of the
primary excavation area. To provide a complete picture of
the observed
responses, representative observations are presented for
the east and west sides of the State Street excavation
and the south side of the Chicago Avenue excavation.
4.1 CONSTRUCTION SEQUENCE AND PROCEDURES
Construction Day 0 corresponds to the beginning
of the secant pile wall installation at the project site.
The construction
days correspond to calendar days and advance sequentially
until the end of construction. The construction days include
weekends and holidays.
The construction activities at the
site are separated into three distinct stages; (i) Stage
1—Wall Installation,
(ii) Stage 2—Support System Installation and Excavation,
and (iii) Stage 3—Station Renovation and Backfill.
The actual beginning and duration of each stage differs depending
on the location within the excavation. However, general groupings
of construction activities are made based on construction
sequence along the (i) east side of the primary excavation
area, (ii) west side of the primary excavation area, and
(iii) the south side of the secondary excavation area. The
time history of the significant excavation and construction
activities that occurred at the site is presented in Table
4-1. The overall construction activity time history for the
project and a structural plan sheet for the station renovations
are given as Appendix A.
Table 4-1. Days of Significant Excavation and Construction
Activity
| Construction Activity |
Day - INCL 1 |
Day - INCL 4 |
Day - INCL 5 |
| Stage 1: Wall Installation |
| Beginning of secant pile wall installation |
2 |
15 |
70 |
| End of secant pile wall installation |
11 |
18 |
79 |
| Stage 2: Excavation
and Support |
| End of strut installation |
74 |
74 |
128 |
| Excavate below upper level tieback/second level struts |
81 |
81 |
1961 |
| Tension upper level tiebacks/Install second level struts |
87 |
91 |
2061 |
| Excavate below lower level tieback |
102 |
98 |
N/A |
| Tension the lower level tiebacks |
105 |
110 |
N/A |
| Excavate to final grade |
116 |
156 |
208 |
| Stage 3: Station Renovation
and Backfill |
| Reduce the bending stiffness of the secant pile wall |
137-140 |
117-134 |
199 |
| Place concrete for escalator bottom slabs |
172-177 |
156-163 |
210 |
| Place backfill |
225-310 |
225-310 |
248-310 |
| Remove struts |
258 |
258 |
235 |
Note: 1 Tiebacks were
not used along the north side of the school. Day corresponds
to second level struts |
4.1.1 Construction Along the East Side of State
Street
The secant pile wall was installed along the entire east
side of the Warde School between Day 0 and Day 30. However,
secant piles directly adjacent to Inclinometer 1 and Inclinometer
2 were installed between Day 0 and Day 11. The locations
of the inclinometers relative to the excavation are shown
in Figure 4-1. The secant pile wall was approximately 18.3
m deep and was constructed by drilling overlapping 915-mm
diameter shafts. Center-to-center spacing of each shaft was
750 mm. Construction of the wall began by first drilling
primary shafts. These shafts were located 1.5 m apart and
were constructed by first auguring down to the clay crust
and installing temporary steel casing. The steel casing was
slightly oversized and provided support for the sand fill
during shaft construction. The remainder of each shaft was
typically drilled uncased. Once the primary shafts were drilled,
W24x55 sections were placed in the holes and a neat concrete
grout was end dumped from concrete trucks. The grout typically
was placed within 2 hours of completing the hole, but occasionally
longer intervals resulted from delays in grout delivery.
Secondary shafts were installed between the primary shafts
by auguring through “green” grout to provide
the 150-mm overlap. Green grout is the condition of the grout
at which it has hardened enough to provide adequate bending
stiffness, yet weak enough so that the edges of the primary
shafts can be removed using conventional drilled shaft equipment.
Typically, the secondary shafts were installed within 24
hours of installing the primary shafts. The design 28-day
compressive strength of the grout was 6.9 MPa. Significant
excavation in a given area did not begin until at least 28
days after the wall in that area had been installed.
The excavation
activities along the east side of State Street occurred
between Day 28 and Day 163. Figure
4-2 shows the profile of the east wall excavation face.
The pipe struts were installed without preload at a depth
of 0.6 m below ground surface. Pipe Struts 1 and 2 were
installed on Day 56 and Day 58, respectively, when the
maximum depth
of the excavation was approximately 3.7 m beneath the struts.
The
maximum excavated grade at the strut locations was an
approximate depth of 4 m during the installation of Strut
3, Strut 4, and Strut 5. Strut 6 was installed when the
excavated
grade at that location reached approximately 4.5 m. Both
levels of tiebacks were installed with excavated grade
no more than 0.6 m below the tieback level. The maximum unsupported
height of the wall was 4.5 m and occurred after the installation
of Strut 6 (Day 79) and prior to stressing the upper level
tiebacks (Day 81). The excavation was advanced to the bottom
depth of 12.2 m at locations adjacent to Inclinometer 1
and
Inclinometer 2 on Day 116. The entire east side was advanced
to the bottom depth of 12.2 m on Day 149. The pit for Escalator
#4 was excavated to a completed depth of 13.7 m on Day
163. The pit for Elevator #3 was also excavated to a final
depth
13.7 m and was completed on Day 165.
The tiebacks were installed
by coring through the secant pile wall and drilling down
to the stiff and hard clay (elevation
-10.7 m CCD). Each tieback was approximately 30.5 m long.
The tieback holes were cased with temporary 178-mm diameter
steel casing in areas where the tiebacks passed through
the softer clays. The upper level tiebacks were cased for
the
first 10.7 m of the hole and the lower level tiebacks were
cased for the first 4.6 m. The steel casing was advanced
using an external water flush. The minimum bond length
for the east side tiebacks was 9.1 m. Once installed, each
tieback
anchor was tested to 1.33 times the design load and the
load was locked off at 80 percent of the design load. Along
the
east side, the design load for the upper and lower level
tiebacks were 278 kN/m and 351 kN/m, respectively. Experience
gained through performance and proof testing showed the
required loads could be attained without regrouting, and
consequently
only about one-half the anchors were actually regrouted.
The
base slab between Stair #7 and Escalator #4 was poured
between Day 172 and Day 177. Other activities of note along
the east side of State Street included pouring the remainder
of the pit slab between Escalator #4 and Elevator #3, pouring
the base slab for the mezzanine, and pouring the exterior
walls of the mezzanine. These activities occurred between
Day 178 and Day 224. A summary of the activities that occurred
during this time can be found in Table 4-1. Backfilling
along
the east side of State Street began on Day 225. Struts
1 and 2 were removed on Day 247. Strut 3 was removed on Day
249 and Struts 4, 5, and 6 were removed on Day 258.
4.1.2 Construction Along the West Side of State
Street
The secant pile wall along the west side of
State Street was installed between Day 0 and Day 37. An abandoned
drift
tunnel was encountered on Day 9 during the installation of
the south end of the west wall. Wall installation activities
at location of the drift tunnel were stopped and were not
resumed until Day 24. The portion of the west secant pile
wall adjacent to Inclinometer 4 was installed between Day
15 and Day 18. The portion of the west secant pile wall involving
the drift tunnel was installed between Day 24 and Day 37.
The days and the sequences in which all the secant piles
were installed along the west side are given in Table 4-1.
The
construction procedures used for the secant pile wall along
the west side of State Street were the same as those
used for the east wall. However, the total installation
time for a single shaft was typically longer for the west
wall
than for the east wall. It took as long as 5 hours after
drilling a shaft for grout to be placed at some locations
along the west wall.
Although some minor excavation activities
began on the south end of the west wall on Day 19, the
excavation along the
west side did not begin in earnest until Day 59. The excavation
activities along the west side of the primary excavation
area were not as consistent as those observed along the
east side. Figure
4-3 presents the profile of the west wall excavation
face. The average depth of the excavated grade was about
2.6 m below ground surface at the time Struts 1, 2, and
3 were installed. Strut 4 was installed on Day 60. At this
time, the depth of excavation was 2.6 m at the Strut 4
location,
but the maximum depth of the excavation along half of the
west excavation face was 5.8 m. From Day 60 to about Day
67, soil from various other excavation activities was stockpiled
in the northwestern corner of the primary excavation area.
About 1/3 of the west side was backfilled to a height of
approximately 1.2 m above the original grade. The stockpile
was removed on Day 74 and excavation activities along the
west side were resumed. Strut 5 and Strut 6 were installed
on Day 74 and Day 79, respectively. The unsupported heights
of the west secant pile wall were limited to a maximum
4 m during excavation, which occurred at the Strut 5 location.
The excavated grade was advanced to depths of approximately
6.1 m and 9.1 m during the installation of the upper and
lower level tiebacks, respectively. The upper level tiebacks
were located at a depth of 4.6 m and the lower level tiebacks
were located at a depth of 8.5 m. The excavated grade was
not more than 1.5 m below the tieback levels during the
installation.
The excavation was advanced to a depth of 11.9 m at the
locations near Inclinometer 4 on Day 117. The excavation
was advanced
to the 11.9-m depth across the entire bottom of the west
side of State Street on Day 137 and remained at that depth
until Day 156.
The excavation was completed to a final
depth of 12.2 m on Day 156. Also at this time, the pit
for the
west side
escalator (Escalator #1) was excavated to a completed depth
of 13.7 m.
The installation procedures used for the tiebacks
along the west wall were very similar to those used for
the east
wall tiebacks. One difference was that the minimum bond
length for the west side tiebacks was 10.7 m. Also, the design
loads
differed from the east side; the upper level tiebacks were
designed for 397 kN/m and the lower level tiebacks were
designed for 429 kN.
The base slab between Stair # 6 and Escalator
#1 was poured between Day 156 and Day 163. All subway station
renovations
along the west side of State Street were completed on Day
224. Backfill activities along the west side commenced
on Day 225.
4.1.3 Construction Along Chicago Avenue
The construction procedures along Chicago Avenue on the
north side of the Warde School differed from those along
State Street. There were no tiebacks used at this location
and the secant pile wall system was only used for about half
the south wall. Soldier piles and lagging were used for the
rest of the wall at this location. A plan view of this configuration
is shown in Figure 4-1. The soldier piles were HP10x42 sections
placed in 510-mm diameter drilled holes. The center-to-center
spacing of the soldier piles was 1.8 m. The combination of
secant pile wall and soldier pile and lagging support systems
were used because the excavation along the north side of
the Warde School was not as deep nor as wide as the excavation
along the west side of the school. The presence of the existing
subway station provided some additional basal stability to
the north side excavation.
Figure
4-4 shows the profile of the excavation along the
north wall. The excavation at this location occurred
between
Day 125 and Day 196. Two levels of cross-lot struts were
installed without preload at depths of 0.9 m and 4.3
m below ground surface. The upper level struts consisted
of HP10x42 sections. The lower struts were HP12x53 sections.
The upper level struts were installed on Day 128 and
Day
133. The excavation was advanced to a maximum depth of
2.1 m on Day 130 and remained at that depth until Day
137. The excavation was advanced to approximately 8.2
m on Day
191 to accommodate the pit for the north side escalator
(Escalator #3). The area west of the escalator pit was
lowered to a final depth of 7 m and the area east of
the pit was completed a final depth of 6.1 m between
Day 191
and Day 196. The lower level struts were installed on
Day 206.
4.1.4 Reduction in the Bending Stiffness of the
Wall
The excavation along State Street was completed
and demolition of portions of the existing subway tunnel
walls began during
the period between Day 110 and Day 140. Prior to backfilling,
portions of the secant pile wall had to be chipped away so
that the required clear span between the east and west mezzanine
walls could be attained. The secant pile walls between Strut
1 and Strut 6 were chipped to the flange of the W24x55 sections
for their entire exposed length. The east wall was chipped
to the flange between Days 110 and 140. The west wall was
chipped to the flange between Days 117 and 134. The majority
of the chipping activities along the north wall occurred
on Day 199. Removal of the hardened grout from the wall resulted
in a reduction in bending stiffness of the wall.
The station
renovations were completed from Day 172 to Day 255. After
the major structural modifications to the station
were completed, the excavation was backfilled. The backfill
activities began on about Day 225.
4.2 OVERVIEW OF FIELD INSTRUMENTATION RESPONSES
Ground movement, building settlement, and pore water pressure
observations are presented and related to the excavation
and construction activities over the extent of the project.
These observations provide summaries of the performance of
the excavation support system and the response of the Warde
School during the project. The instrumentation data collected
during the course of the project are presented as Appendix
B. The optical survey data is given in Table B-1. Table B-2
presents the pore water pressure data. The strain gauge data
for the struts are given in Table B-3 and Table B-4 presents
the load cell data for selected tiebacks. The inclinometer
data is presented in Table B-5. It is noted that the only
the A-axis data is presented for Inclinometers 1, 2, 4, and
5. The B-axis data for these inclinometers showed that the
ground movement parallel to the plane of the excavation was
relatively small at the inclinometer locations. Therefore,
this data was not included. Also, the deformations recorded
at Inclinometer 3 during the project were negligible and
thus not used in any of the analyses. As a result, the Inclinometer
3 data are not included in Appendix B.
4.2.1 Ground and Building Movements
4.2.1.1 Responses along East Side of State Street
Lateral ground movements resulting from the
excavation and construction activities along the east side
of State Street
are evaluated using the Inclinometer 1 and Inclinometer 2
responses. These lateral movements are compared to settlement
data obtained from points on the Warde School adjacent to
the inclinometer locations. Although Inclinometer 2 was also
located along the east side of the State Street, its data
were locally affected by installation of a tieback. As a
result, the lateral movements observed for Inclinometer 2
near elevation -3.4 m CCD were not completely representative
of the lateral response of the clay at that elevation.
Summaries
of the movements that developed throughout construction at
these locations are presented in Figure
4-5 and Figure
4-6. These figures show deformations plotted against
time for the duration of the project. The horizontal movements
were measured for both inclinometers at depths corresponding
to the maximum lateral deformation: (i) within the soft clay
(elevation -3.7 m CCD), (ii) at the bottom of the excavation
(elevation -7.9 m CCD), and (iii) in the stiff clay below
the bottom of the excavation (elevation –11.0 m CCD).
The
Inclinometer 1 and 2 deformations in Figure 4-5 and Figure
4-6 are the lateral movements perpendicular to the
secant pile wall in the east-west direction. Inclinometer
1 and Inclinometer 2 were located approximately 2.2 m and
1.7 m west of the school, respectively. The settlement
shown in Figure 4-5 was obtained from optical survey data
at settlement
point W10 on the west exterior wall of the Warde School
near Inclinometer 1 (see Figure 3-2). The settlement shown
in
Figure 4-6 was obtained from survey data at settlement
point W8, near Inclinometer 2 (see Figure 3-2). Settlement
point
W10 was located approximately 2.2 m east of Inclinometer
1 and settlement point W8 was located about 1.7 m east
of Inclinometer 2. Also plotted in Figures 4-5 and 4-6 are
the
major construction activities at the Inclinometer 1 and
Inclinometer 2 locations.
It is apparent from both figures
that the settlement of the building follows the development
of lateral movements
in the soil. The lateral movements within the soft clay
(elevation -3.7 m CCD) and the settlements at W8 and W10
were virtually
identical until Day 145 when excavation was complete and
the secant pile wall had been chipped to the flange at
both inclinometer locations. Thereafter, the settlements
became
slightly greater than the maximum lateral movements. Of
the approximately 40 mm of lateral deformation measured at
Inclinometer
1, 10 mm occurred during wall installation, 18 mm developed
as the soil was excavated and the lateral support installed,
and 12 mm occurred during tunnel demolition and station
renovation as a result of creep and the reduction of wall
stiffness.
The maximum amount of lateral deformation at
Inclinometer 2 was about 10 mm less (30 mm total) than was
observed at
Inclinometer 1. Similar to what was observed at Inclinometer
1, 10 mm of deformation occurred during wall installation.
About 12 mm of deformation at Inclinometer 2 was attributed
to installation of the support system and excavating to
the final grade. From Figure 4-6, it is noted that there
is a
sharp dip in the elevation -3.7 m CCD curve at Day 74.
This dip is a result of installing the upper level tieback
at
that location. This response is presumably a very local
effect and, hence if the tieback did not pass so close to
Inclinometer
2, then more deformation would have been recorded in the
soft clay. The last 8 mm of deformation occurred in response
to the reduction of wall stiffness and creep.
Figures 4-5
and 4-6 show that lateral movements and settlement first
occurred as the secant pile wall was installed. The
movements increased very slightly during the installation
of the struts and the upper level tiebacks. However, both
figures indicate a rapid increase in movements once the
excavation was advanced below the stiff clay crust at elevation
-1.2
m CCD. Both figures show a dramatic reduction in the rate
of deformation once the excavation is completed, between
Day 114 and Day 116. However, both figures show an increase
in the rate of movement between Day 150 and Day 175. This
increase was caused by the reduction in wall stiffness
caused by chipping away the face of the secant pile wall.
Placing
the base slab between Day 172 and Day 177 at both the Inclinometer
1 and the Inclinometer 2 locations reduced
the rate of lateral movements. This was because the slab
acted as a diaphragm once it abutted the existing tunnel.
Note that the movements associated with stress
relief from the excavation were less than one-half the total
movement.
This is significant in that the movements associated
with stress relief during excavation and support placement
are
many times the only ones considered when predicting the
movements associated with deep excavations.
4.2.1.2 Responses along West Side of State Street
Lateral ground movements resulting from the excavation and
construction activities along the west side of the State
Street are evaluated using the responses observed at Inclinometer
4. Summaries of the movements that developed throughout construction
at Inclinometer 4 are presented in Figure
4-7. Similar to Figure 4-5 and 4-6, deformations are
plotted versus time and the horizontal movements are measured
at depths corresponding to the maximum lateral deformation:
(i) within the soft clay (elevation -4.4 m CCD), (ii) at
the bottom of the excavation (elevation -8.1 m CCD), and
(iii) in the stiff clay below the bottom of the excavation
(elevation -11.1 m CCD). The excavation and construction
activities shown above the deformation curves in Figure 4-7
are applicable to the area adjacent to Inclinometer 4. The
figure shows that the values between Day 109 and Day 123
were estimated. The original Inclinometer 4 was destroyed
while installing a sanitary sewer line on the west side of
State Street.
A new inclinometer was installed approximately
1 m north of the original location. Based on the deformation
trends
observed at Inclinometers 1 and 2 at this same time, it
was assumed that the increase in lateral movements at Inclinometer
4 were relatively linear between Days 109 and 123. Consequently,
the deformations shown in Figure 4-7 by the dashed lines
were extended to Day 123 at the slope observed prior to
the
inclinometer being damaged. The deformations after Day
123 were obtained by adding measured deformations from the
new
inclinometer to the estimated cumulative value at the end
of Day 123.
It is observed from Figure 4-7 that the general
lateral deformation trends on the west side of the excavation
are
very similar to those on the east side. However, the magnitude
of deformation on the west side of State Street was approximately
30 percent greater than on the east side.
An estimated 57
mm of lateral deformation was measured within the soft
clay layer at Inclinometer 4. Of this total deformation,
approximately 17 mm occurred during the wall installation.
This deformation represents 34 percent of the total lateral
deformation measured within the soft clay layer. An additional
36 mm (59 percent of the total) of lateral deformation
was measured during the excavation and support installation
stage
and the remaining 4 mm (7 percent of the total) of deformation
occurred during the station renovation. Thus, just a little
more than half of the lateral deformations measured on
the west side are in response to excavation-induced stress
relief.
The percentages of movements caused by excavation-induced
stress relief are similar to those observed on the east
side, where 45 percent of the total lateral deformation developed
in the soft clay as a result of this factor.
From Figure
4-7, it is noted that the majority of lateral deformations
resulting from stress relief did not occur until
the excavation was advanced about midway into the soft
clay layer at elevation -1.8 m CCD. This is apparent from
observing
that the lateral deformation measured at elevation -4.4
m CCD only increased from 17 mm to about 20 mm from Day 25
to Day 92. The corresponding change in the excavated depth
during this time was from elevation +4 m CCD to elevation
-1.8 m CCD. However, as the excavation was advanced from
that point to the final elevation of -8.2 m CCD (Day 93
to
Day 156), the lateral deformation increased from 20 mm
to an estimated 53 mm. Along the east side, the significant
increase in lateral movements occurred once the excavation
was advanced below elevation -1.2 m CCD.
Figure 4-7 shows
that the rate of deformation appeared to slow between Day
120 and Day 130, but then began to increase
after Day 130 at the previous rate. The decrease in the
deformation rate was in response to the excavation being
stalled at elevation
-7.6 m CCD. The increase in the rate of deformation corresponds
to advancing the excavation to its deepest point (elevation
-8.2 m CCD) beginning on Day 137 and chipping the secant
pile wall between Day 117 and Day 134. The excavation was
completed at Inclinometer 4 location on Day 156 and the
pit slab for Escalator #1 was completed on Day 163. Only
minor
creep movements (approximately 4.4 mm) were observed after
the pit slab was completed.
4.2.1.3 Responses along Chicago Avenue
Figure
4-8 presents the lateral deformations measured at Inclinometer
5 located between the school and the excavation along Chicago
Avenue. These deformations represent the lateral movements
at the north side of the Warde School. The figure shows
deformations in both the east-west (B-axis) and north-south
(A-axis) directions. The depths at which the lateral movements
were measured corresponded to: (i) the depth of maximum
lateral deformation for Inclinometer 5 (elevation -2.6
m CCD), this also corresponds to the bottom of the excavation
on the north side of the Warde School; (ii) the bottom
of the Blodgett layer (elevation -6.8 m CCD); and (iii)
the bottom of the Deerfield layer (elevation -9.9 m CCD).
Also shown in Figure 4-8 are the settlement data obtained
from settlement point W13. This settlement point was adjacent
to the Inclinometer 5 location. Two excavation profiles
are given in Figure 4-8, one represents the construction
record at Chicago Avenue at the Inclinometer 5 location,
and the other represents the construction record at the
northwest corner of the school.
Although the north-south
direction was the primary direction of measurement, it
is apparent that the east-west direction
represented a significant component of the movement. The
total lateral movement is represented by the resultant
of the A- and B-axis movements and is also shown on the figure.
Figure 4-8 shows that the lateral deformations in the east-west
direction were consistently greater than those in north-south
direction throughout the project. More importantly, the
resultant
of the two components of the lateral movement tracks the
development of the surface settlement much better than
either of the individual components.
The north secant pile
wall was installed between Day 70 and Day 79. In response
to this activity, the maximum lateral
deformation perpendicular (north-south component) to the
secant pile wall was about 4 mm, but the maximum lateral
deformation parallel (east-west component) to the secant
pile wall was about 10 mm.
Presumably, the increase in the
east-west component on Day 79 was in response to the excavation
at the northwest corner
being lowered beneath the clay crust. The figure shows
that the excavated grade at the northwest corner of the east
secant
pile wall was advanced to approximately elevation -1.2
m CCD on Day 79. The excavation activities on the north side
of the Warde School occurred between Day 125 and Day 208.
During this period, the north-south component of the maximum
lateral deformation increased from about 4 mm to about
14
mm and the east-west component of the maximum lateral deformation
increased from 10 mm to 20 mm. During this time, the excavated
grade at the northwest corner was advance from elevation
-6.4 m CCD to elevation -8 m CCD on Day 150. The excavated
grade at the Inclinometer 5 location was not advanced below
the clay crust until about Day 170. It appears that, at
least until Day 170, the east-west component of lateral movement
was primarily in response to the excavation along State
Street.
There were no additional lateral deformations observed
after the pit slab was pour. The pit slab acted as a continuous
support across the bottom of the excavation.
The optical
survey data showed that from Day 70 to Day 79 the settlement
at W13 increased from 6 mm to 11 mm. By comparing
this settlement with the resultant lateral deformations
at elevation -28 m CCD, which also increased to the 11 mm
during
this time, one can see that the settlements were caused
by the combined effects of the installation of the north
secant
pile wall and the excavation along State Street. Figure
4-8 shows that the settlement rate increased after Day 170,
as
a result of excavating below the clay crust along Chicago
Avenue. The settlement increased to a maximum of about
28 mm on Day 208. These settlement responses indicate that
the
deformational behavior of the northwest corner of the building
was a function of the 3-D excavation geometry at that location.
4.2.2 Pore Water Pressure Response
Pneumatic piezometers were installed at elevations -5.8
m CCD and -8.8 m CCD adjacent to Inclinometer 1 and at elevations
-6.4 m CCD and -9.45 m CCD adjacent to Inclinometer 4. These
piezometer locations were designated Piezometer 1 and Piezometer
4 to correspond to the inclinometer locations Piezometer
1 was located 2 m from the secant pile wall whereas Piezometer
4 was located 3 m from the wall. Data were collected at both
piezometer locations throughout the project. However, the
piezometers at the Piezometer 1 location were destroyed during
installation of the upper level tiebacks. Figure
4-9 presents the pore water pressure responses at the
Piezometer 1 location, up to the day the piezometers were
destroyed. The pore water pressure responses at the Piezometer
4 location are presented in Figure
4-10. The figure uses two colors for each piezometer
curve. This is because the original piezometers at this location
were destroyed as a result of the west side construction
activities. New piezometers were installed at the same depths
of the original piezometers, a few feet north of the original
location. The first color in each curve represents the pore
water pressure data from the original piezometers and the
second color is the replacement piezometers. Note that there
was some overlap for the piezometer at elevation -9.45 m
CCD.
Similar responses were observed at both the
Piezometer 1 and Piezometer 4 locations. The data obtained
before construction
began indicate that essentially hydrostatic conditions
initially existed in the clays. The elevation of the piezometric
surface
at the Piezometer 4 location was approximately +0.75 m
CCD and the piezometric surface at the Piezometer 1 location
was approximately +0.6 m CCD. The piezometric surface is
slightly above the top of the stiff clay crust layer and
is apparently sloping towards Lake Michigan.
Figures 4-9
and 4-10 show that large drops in water pressure occurred
as the secant pile wall was installed. The water
heads dropped as much as 5.5 m at the Piezometer 1 location
and about 4.5 m at the Piezometer 4 location. Essentially,
the open shafts of the secant piles near the piezometer
locations acted as temporary sinks. Because grout was placed
within
each of the holes soon after excavation, the water levels
at Piezometer 4 recovered most of their initial values
within about 38 days. The excavation had not proceeded below
the
clay crust at this time (Figure 4-10). The water levels
at Piezometer 1 had recovered about 82 percent of their initial
values before the excavation was advanced below the clay
crust on Day 60. Afterwards, the water levels dropped in
response to the excavation until the piezometers were destroyed
on Day 87. From this point, the Piezometer 4 data are used
to illustrate the pore pressure responses to the subsequent
construction activities.
The pore pressures at Piezometer
4 were relatively steady from about Day 38 to Day 90. Thereafter,
the excavation along
the west side was lowered below elevation -1.8 m CCD, whereupon
the pore pressures began to drop. This time corresponds
to the time where the clay crust was excavated and significant
movements began to develop during excavation. Another transient
response was observed when the second level tiebacks were
stressed. Water heads increased as much as 5 m, but dissipated
within several days. Given that the anchors passed within
2 m of both piezometers and that the pressures rapidly
dissipated,
the pore pressure responses caused by stressing the anchors
were localized. By Day 150, the water levels had dropped
about 3 m from their initial values at both piezometers.
This drop increased the effective stress in the soft clay
by 30 kPa, apparently enough for small consolidation settlements
to develop. If one assumes that the pore pressures on both
sides of the excavation responded to the construction activities
in a similar manner, the data beyond Day 150, shown in
Figure 4-5, can be interpreted in light of these pore pressure
changes.
At settlement point W10, movements larger than observed
in the inclinometer data at elevation -3.7 m CCD began to
develop.
These movements were presumably a result of the small consolidation
settlement arising from the drop in water pressure. The
maximum excavation-related drop in the water level was observed
on
Day 203, prior to backfilling. At this time, the heads
in the piezometers were 7.1 m at elevation -9.45 m CCD and
4.5
m at elevation -6.4 m CCD. After Day 203, the pressures
began to recover slightly. However, after backfill was completed
on Day 354, water levels remained about 2.4 m below the
initial
values. The water levels should increase slowly over time
depending on the effectiveness of the waterproofing for
the renovated station.
4.3 DETAILED OBSERVATIONS OF LATERAL MOVEMENTS
Detailed observations of lateral movements
are given for locations corresponding to the excavation activities
along
the east and west sides of State Street and along Chicago
Avenue. Inclinometer 1 is representative of the east side
of State Street, because the lateral responses at Inclinometers
1 and 2 were very similar (see Section 4.2.1.1). Inclinometer
4 was used to represent the west side of State Street and
Inclinometer 5 is representative of the activities along
Chicago Avenue.
The detailed observations include inclinometer
responses to significant excavation and construction activity.
Activities
common to all three locations are given in Table 4-1. The
table shows the activities and the days of occurrences
at the three locations. Note that the activities are listed
in groups of the major construction stages of the project.
The subsequent sections discuss the lateral movements observed
at the Inclinometer 1, 4, and 5 locations during each construction
stage.
4.3.1 Stage 1 – Wall Installation
Table 4-1 indicates that the secant pile wall installation
activities at the representative inclinometer locations along
State Street (Inclinometer 1 and Inclinometer 4) were completed
between Day 2 and Day 18. The table also shows that the secant
pile wall was installed along Chicago Avenue between Day
70 and Day 79. However, these dates only include the installation
of the secant piles that influenced the responses of the
inclinometers. Using a trail-and-error method of comparing
secant pile installation with inclinometer response, it was
ascertained that the inclinometer responded to installation
activities when secant piles were being installed at a center-to-center
spacing of 3.8 m. Referring to Table A-1 in Appendix A, it
is seen that the entire east secant pile wall was installed
between Day 0 and Day 30. The complete west secant pile wall
was installed between Day 9 and Day 32. The dates given in
Table 4-1 for the Inclinometer 5 location include installation
of all the secant piles along Chicago Avenue.
4.3.1.1 East Side of State Street
Figure
4-11 presents the lateral responses for Inclinometer
1 and the settlement response of the Warde School at a
section perpendicular to the east secant pile wall through
Inclinometer 1. The inclinometer was located 2.3 m from
the centerline of the secant pile wall. This section is
typical of the response in the middle of the east secant
pile wall and shows the effects of construction on the
Warde School. Lateral soil movements developed as the wall
was installed with the maximum movement occurring within
the soft clay. Note that the stability number (Peck, 1969)
of the clay at the depth of maximum movement was 7.8. This
high stability number would suggest that inward movements
would occur due to stress relief as a shaft was drilled
without support (i.e., with no drilling mud or casing).
The lateral movements extend to the depth of the secant
pile wall. The building settled as much as the soil displaced
laterally, with the settlement extending as far behind
the excavation as the secant pile extended below the bottom
of the school’s foundation. These patterns of movement
are expected because the movements into the shafts of the
secant pile wall are the result of undrained deformations
in saturated clay.
Figure
4-11 shows that the maximum lateral
deformation at the end of the secant pile wall installation
(Day 11) was
approximately 10 mm. This initial 10 mm of deformation
corresponded to about 26 percent of the total lateral deformation
observed
along the east secant pile wall. The figure also indicates
that below the soft clay layer, the inflection points of
the deformation curves correspond approximately to the
layer interfaces. This trend is likely the result of the
differences
in shear strength and stiffness among the layers. Peck
and Reed (1954) indicated that the undrained shear strength
of
individual strata in the downtown area of Chicago generally
increases in steps from one stratum to the next.
4.3.1.2 West Side of State Street
Figure
4-12 presents the lateral soil movements during wall
installation at the Inclinometer 4 location. The inclinometer
was located approximately 3 m from the centerline of the
west secant pile wall. The figure shows that the maximum
deformation of 17 mm observed at the end of the secant
pile wall installation was greater than what was observed
at Inclinometer 1. The point of maximum deformation occurred
in the medium clay layer at elevation -5 m CCD. The larger
lateral movements at Inclinometer 4 reflect the shafts
of the west wall secant piles being open for longer times
prior to placing the concrete. Along the east secant pile
wall, steel casing was advanced well into the soft clay
when constructing shafts near the Inclinometer 1 location
and concrete was typically placed within 2 hours of drilling
the shafts. However, along the west secant pile wall the
steel casing was only advanced to the stiff clay layer
and, in some instances, the steel casing was not used at
all. In addition, concrete placement for the west secant
pile wall sometimes took as long as 5 hours after drilling
the shaft.
Another factor contributing to the larger lateral
movements at Inclinometer 4 are the higher insitu soil
stresses on
the west side of the excavation. Construction of the Warde
School decreased the insitu stress state along the east
side of the project site as a result of the net unloading
associated
with the excavation of the basement and the reloading associated
with the construction of the building. Thus, for the same
undrained shear strength, the stability number is higher
on the west side of the excavation than on the east side.
As a result, soil squeeze into the open, uncased shaft
and the subsequent ground loss will occur faster and be greater
on the west side of the excavation than on the east side.
No settlement data were recorded on the west side of the
excavation.
4.3.1.3 Chicago Avenue
Figure
4-13 gives the lateral soil response for Inclinometer
5. The inclinometer was located 700 mm south of the centerline
of the north secant pile wall and represents the lateral
soil response along the north side of the Warde School.
The figure gives the lateral movements in the direction
towards Chicago Avenue (4-13a) and the movements in the
direction towards State Street (4-13b).
It should be noted
that the inclinometer was damaged several times during
the installation of the secant pile wall along
Chicago Avenue (refer to Table A-1 in Appendix A). Consequently,
the upper 3.5 m to 4 m of the data reflects movements caused
by impacts against the inclinometer casing and not lateral
deformations of the soil resulting from wall installation.
More reliable lateral deformation data were observed below
elevations corresponding to the middle of the stiff clay
crust (approximately elevation +0.6 m CCD). As was the
case in other inclinometers, it is apparent that maximum
wall
installation-related deformations occurred within the soft
clay layer. However, the magnitude of maximum deformation
in the direction perpendicular to face of the excavation
was about 40 percent of that observed at the Inclinometer
1 location during wall installation along State Street.
Figure 4-13a gives the maximum deformation in response to
wall installation
for Inclinometer 5 as approximately 4 mm, as compared to
10 mm at Inclinometer 1. Figure 4-13b shows that the maximum
lateral deformation at Inclinometer 5 in the direction
toward State Street was just slightly less than 10 mm on
Day 79,
of which 6 mm occurred as a result of installing the wall
between Day 70 and 79. The decidedly 2-D movement in response
to wall installation was caused by the fact that Inclinometer
5 was located within 0.8 m of the wall, and thus was affected
locally in two directions by the drilling operations. As
was noted for the other inclinometer locations, inflection
points along the depth of the curves were observed at the
approximate layer interfaces. The bottom of the secant
pile wall served as the lower bound for the lateral movements.
4.3.2 Stage 2 – Excavation and Support System
Installation
Stage 2 covers the period of excavation and support system
installation. The struts along State Street were installed
between Day 60 and Day 74. All upper level tiebacks for both
the east and west secant pile walls were completed as of
Day 106 and all lower level tiebacks were completed as of
Day 114. The struts along Chicago Avenue were installed between
Day 128 and Day 206. No tiebacks were used on the north side
of the Warde School. Dates given in Table 4-1 for strut and
tieback installation are for the struts and tiebacks in the
vicinity of the inclinometers only. Refer to Appendix A for
a complete record of the support system installation.
4.3.2.1 East Side of State Street
Figure
4-14 presents the Stage 2 lateral deformations observed
along the east secant pile wall. The grade was excavated
to elevation +2.7 m CCD on Day 59. Negligible movement
occurred from the end of wall installation to when the
excavation was lowered to elevation +2.7 m CCD. Significant
lateral movements began to develop as the excavation was
advanced through the clay crust. This large increase in
movements was due to the reduction in the basal heave factor
of safety. Clough et al. (1989) defined the factor of safety
against basal heave for relatively wide excavations (H/B < 1)
as
where H is the depth of the excavation, B is
the effective width of the excavation, Nc is the
bearing capacity factor, Suu is the undrained
shear strength above the bottom of the excavation, Sub is
the undrained shear strength below the bottom of the excavation,
and γ is
the total unit weight of the soil above the bottom of the
excavation. Note, the presence of the tunnel restricts the
width of the failure zone. Thus, to account for the limited
failure zone, the top of the tunnel is used as a rigid base.
Table 4-2 gives the basal heave parameters prior to the excavation
advancing below the stiff clay crust and after the excavation
has advanced into the soft clay. The undrained shear strength
values above the bottom of the excavation were obtained from
the weighted averages of the layers within the depth H. The
undrained shear strength values below the bottom of the excavation
are the average values within the failure zone. From Table
4-2, it can be seen that the factor of safety decreased by
about 53 percent after the excavation was advanced below
the clay crust
| Basal Heave Parameters |
Excavation at Clay Crust Layer (bgs) |
Excavation at Soft Clay Layer (bgs)
|
| H |
5.5 m |
6.5 m |
| B |
2.6 m |
2.6 m
|
| L (length of excavation) |
35 m |
35 m |
| Nc |
7.1 |
7.3 |
| γ |
19.63 kN/m3 |
18.94 kN/m3 |
| Suu |
30 kPa |
23 kPa |
| Sub |
15 kPa |
15 kPa |
| Factor of Safety (FS) |
5.8 |
2.7 |
| Note: (1) bgs = Below ground surface |
Figure 4-14 shows that the lateral movements extend to the
depth of the secant pile wall. The building settled as much
as the soil displaced laterally, with the settlement extending
as far behind the excavation as the secant pile wall extended
below the bottom of the school’s foundation. The equality
of lateral movements and settlements are expected because
the movements that occur are essentially undrained.
Figure
4-14 shows that the incremental deformations increased
slightly more than 2 mm as the excavation was advanced below
the first tieback level (elevation -1.4 m CCD) on Day 81,
and an additional 3 mm before stressing the first level
tieback
on Day 87. The increment of movement between excavating
below the first tieback level on Day 81 and excavating below
the
second tieback level (elevation -5.2 m CCD) on Day 102
was about 9 mm, resulting in a cumulative deformation of
21 mm.
The upper portion of the wall moved about 2 mm toward the
soil both times the tiebacks were stressed. As a result,
the rate deformation was temporarily halted at each instance
the tiebacks were stressed. This can be seen from the response
of the soft clay layer in Figure 4-5. After the tiebacks
were stressed, the secant pile wall moved incrementally
toward the excavation in response to excavation-induced stress
relief.
The excavation was lowered to the final elevation of -7.9
m CCD on Day 116. When the excavation reached final grade,
the maximum lateral movement increased to 28 mm. The school
settled as the secant pile wall moved laterally.
The maximum
settlement of the school at the end of excavation was equal
to this maximum lateral movement of 28 mm. Note
that the extent of the settlement trough did not increase
during this time.
4.3.2.2 West Side of State Street
The observed and estimated Stage 2 lateral deformations
for Inclinometer 4 are presented in Figure
4-15. As was discussed in Section 4.2.1.2, the original
Inclinometer 4 was destroyed on Day 109. Values reported
after that date were estimated based on incremental data
from the new inclinometer and observed trends of increase
in lateral movements at Inclinometers 1 and 2. The lateral
movements at Inclinometer 4 during this stage were about
twice those observed at Inclinometer 1. The excavation along
west secant pile wall was advanced below the strut level
(elevation +2.7 m CCD) on Day 59 with no significant lateral
movements. Significant lateral movements again developed
as the excavation was advanced through the clay crust. Two
millimeters of movement occurred as a result of advancing
the excavation below the first level tieback to elevation
-1.8 m CCD on Day 81. Note that the shape of the deformation
curves indicated cantilever movement of the wall until the
first level tieback was installed on Day 81. This large cantilever-type
movement is in contrast to that observed on the east side
of the excavation, where very little cantilever movement
was observed. Apparently, load from the west side of the
excavation was being transferred to the east side through
the struts, resulting in larger cantilever-type movements
on the west side.
The increment of movement between excavating
below the first tieback level on Day 81 and excavating
below the second tieback
level (elevation -4.9 m CCD) on Day 98 was about 12 mm.
This is compared to the 9 mm of incremental movement at Inclinometer
1 for the same excavation activity, even though a greater
height of the wall was unsupported along the east side
than
was observed on the west side prior to stressing the second
level tieback. The maximum lateral deformation increased
to 43 mm on Day 123, which corresponded to the excavation
along the west side being advanced to elevation -7.6 m
CCD. The stress relief-induced movements continued to increase
until the excavation reached final grade at elevation -8.2
m CCD on Day 156. The maximum lateral deformation was 57
mm on Day 156. From the shape of the lateral response curves
shown in Figure 4-15, it is observed that deep inward movement
of the secant pile wall characterized the incremental lateral
deformation when the excavation was lowered from the second
tieback level to final grade.
The secant pile wall was
chipped from elevation -4.26 m CCD to elevation -7.62
m CCD between Day 117 and Day 134.
This
process resulted in the wall becoming more flexible
and ultimately contributed to the increase in lateral movements
in the soft
clay layer.
4.3.2.3 Chicago Avenue
The lateral deformation measured at Inclinometer
5 for the Stage 2 construction activities are presented in Figure
4-16. The lateral movements toward Chicago Avenue are
given in Figure 4-16a while those toward State Street are
shown in Figure 4-16b. The depth of the excavation along
the north side of the Warde School was about half that along
State Street. Consequently, the maximum lateral movements
along north secant pile wall are smaller than those observed
on either side of State Street.
Cumulative lateral movement
at Inclinometer 5 was 3 mm in the north-south direction
and 11 mm in the east-west direction
on Day 109. At this time, the north side excavation was
extended to below the upper strut level at elevation +2.1
m CCD. An
additional 2 mm of movement was observed in the north-south
direction between the initial excavation and installing
the upper level strut on Day 128. No movement was observed
in
the east-west direction during this time. The excavation
along the north side was first advanced into the soft clay
layer (elevation -1.5 m CCD) on Day 170. This resulted
in a maximum incremental movement toward Chicago Avenue of
2
mm and maximum incremental movement towards State Street
of 4 mm, clearly showing the effects of the excavation
on State Street.
Figure 4-16 shows that after Day 170 the
incremental movements were primarily directed towards Chicago
Avenue as a result
of excavating from -1.5 m CCD to -4 m CCD on Day 208. The
increment of lateral deformation in the soft clay between
Day 170 and Day 208 was 7 mm toward Chicago Avenue and
1 mm toward State Street. There were no additional excavation
activities along the east side of State Street after the
pit for Escalator #3 was completed on Day 163. Thus, deformations
observed after Day 163 were primarily caused by excavation
activities along Chicago Avenue, although small amounts
of
creep movements may have developed as well. Note that at
the Inclinometers 1 and 2 locations creep movements were
observed after the excavation activities had been completed.
It was observed that the rate of creep at these two inclinometers
produced an increment of maximum movement in the soft clay
layer of about 2 mm for a given 38-day period. This maximum
increment of movement compares to the 1-mm increment toward
State Street observed at Inclinometer 5 between Day 170
and Day 208.
4.3.3 Stage 3 – Renovation and Backfill
The last major stage in the Chicago Avenue and State Street
subway renovation project involved completing the capital
improvements and backfilling the excavation. Table 4-1 indicates
that this stage began with chipping the secant pile wall
adjacent to the inclinometer locations. However, chipping
of the secant pile wall occurred prior to completing the
excavation at the Inclinometer 4 and Inclinometer 5 locations.
4.3.3.1 East Side of State Street
The lateral deformations measured at Inclinometer 1 during
this stage of the construction are presented in Figure
4-17. Very small creep movements developed after the
excavation was advanced to final grade. This can be seen
from the incremental movement between Day 116 and Day 137.
To
accommodate the exterior walls of the new mezzanine section,
the grout on the face of the secant pile wall was chipped
to the face of the flange from elevations -4.3 m to -7.6
m CCD between Days 137 and 140. This chipping activity
resulted in a reduction of the bending stiffness of the wall.
Consequently,
more movements were observed between Days 137 and 176,
when the bottom slab for Escalator #4 was poured, than were
observed
during the remainder of this stage of construction. Reducing
the stiffness of the wall resulted in approximately 5 mm
of incremental movement within the softer clays. After
Day 176, approximately 3 mm of small creep movements continued
until the excavation was completely backfilled. Note that
the tiebacks were not cut, and remain stressed in place.
Removal of the top level of bracing on Day 258 resulted
in
small cantilever movements near the top of the wall, as
is evident from the Day 266 curve in Figure 4-17.
4.3.3.2 West Side of State Street
The estimated lateral deformations measured at Inclinometer
4 for Stage 3 are presented in Figure
4-18. The base slab for Escalator #1 was completed on
Day 163 and the backfill was placed between Day 225 and Day
310. A total of 3 mm of incremental creep movement was observed
between the time when the escalator bottom slab was placed
and backfill was completed. The west secant pile wall was
also chipped to the flange along its exposed length However,
unlike the east secant pile wall, the west secant pile wall
was chipped prior to advancing the west side excavation to
final grade. The chipping activities occurred between Day
117 and Day 134 and the excavation along the west side was
completed on Day 156. Hence, the incremental lateral wall
movements given in Figure 4-18 are a result of creep and
strut removal.
4.3.3.3 Chicago Avenue
Figure
4-19 presents lateral deformations measured at Inclinometer
5 during Stage 3. It is apparent from the figure that little
movement occurred along the north side of the Warde School
after the excavation was advanced to final grade on Day
208. Very minor creep movements in the direction of State
Street were observed after the base slab for Escalator
#3 was poured (Day 210). There were no additional lateral
movements observed in the direction of Chicago Avenue after
the base slab was pour. The base slab effectively acted
as an additional support level across the bottom of the
excavation.
4.3.4 Summary of Lateral Deformations and Discussion
4.3.4.1 Incremental Lateral Soil Movements
Figure
4-20 shows a comparison of the lateral increments of
movements that occurred adjacent to the excavation at Inclinometers
1, 2, 4, and 5. The incremental movements are shown for
the three stage of construction: wall installation (20a),
excavation to final grade (20b), and station renovation
and backfill (20c).
Inclinometers 1 and 2 along the east
side of the excavation exhibited very similar responses,
with the exception of the
kink in the data at elevation -3.4 m CCD at Inclinometer
2. This kink was the result of installing a first level
tieback next to the inclinometer. Inclinometer 4 along the
west side
of the excavation showed incremental movements that were
about 50 percent larger than those on the east side. Incremental
movements along the north side at Inclinometer 5 were about
50 percent less than those on the east side.
During wall
installation, 17 mm of lateral movement developed at the
Inclinometer 4 location, which was about twice that
at the other locations. The magnitude of this movement depended
on the amount of time the shafts remained open after it was
drilled and before it was filled with grout. Near the location
of Inclinometer 4, the shafts remained open for as long as
5 hours, as compared to times of no more than 2 hours along
the east side of the excavation. During excavation, the increment
of movement was about twice as much along the west wall compared
to that along the east wall and about four times as much
as that along the north wall. The large difference in incremental
movements between Inclinometer 4 and Inclinometer 5 was primarily
due to the different depths of excavation and the geometry
of the excavation adjacent to the inclinometer. However,
along the east side the excavation the depth and geometry
of the excavation and the construction sequences were similar
to that along the west side. The larger movements observed
during the wall installation at the Inclinometer 5 location
apparently impacted the subsequent movements. As the soil
deformed more into the open shaft, the soil mobilized its
shear strength, leaving less available resistance for stresses
imposed by subsequent excavation. Cunningham and Fernandez
(1972) observed similar responses. They reported larger movements
during excavation at locations where larger movements occurred
as large diameter caissons were installed near a slurry wall
before the excavation began. The presence of surcharge loads
on the west side, in the form of construction equipment and
materials, could have also contributed to the larger movements.
No such loads were imposed on the east side of the excavation
because of the lack of space between the secant pile wall
and the school. Another contributing cause to the larger
incremental movements during excavation could be the higher
insitu stresses in the soil on that side of the excavation.
There were no buildings on the west side, whereas the 3–story
Warde School with its 3-m deep basement imposed less stress
on the wall than the soil on the west side.
The smaller creep
movements along the west secant pile wall can be attributed
to the base slab being placed more quickly
at that location than along the east wall. The creep movements
along the north wall were negligible because the excavation
was extended only partially into the soft clay layer.
4.3.4.2 Lateral Deformation Vectors
Figures 4-13, 4-16, and 4-19 indicated that although the
north-south direction (towards Chicago Avenue) was the primary
direction of measurement for Inclinometer 5, a significant
component of the movement was in the east-west direction
(towards State Street). This suggests that the lateral movements
observed at Inclinometer 5 were heavily influenced by excavation
activities performed along the west side of the school. Prior
to excavating to final grade, the magnitudes of movements
in the east-west direction were greater than those observed
in the north-south direction. The implication is that the
movements resulting from the excavation-induced stress relief
at the corner were a function of the 3-D geometry of the
excavation. Thus, in order to compare the lateral deformational
response of Inclinometer 5 with those of Inclinometer 1 and
Inclinometer 2, the deformations at Inclinometer 5 are presented
in term of the deformation resultant. The movements towards
Chicago Avenue serve as the northern component of the resultant
and the movements towards State Street serve as the western
component. Figure
4-21 presents a plan view of the lateral deformation
vectors measured at Inclinometers 5, 1, and 2 to show the
effects of opening the excavation along Chicago Avenue at
the same time as the State Street excavation. The deformations
are given at depths within the soft clay stratum corresponding
to the maximum observed lateral movements in the inclinometers.
For Inclinometer 1, the depth of maximum movement was 7.9
m below ground surface. The depth of maximum movement for
Inclinometer 2 was 8.6 m and the depth for Inclinometer 5
was 6.9 m. The construction days used in the figure correspond
to the days of significant construction activity presented
in the previous sections.
Figure 4-21 shows that the ground
movement was nearly perpendicular to the State Street excavation
at the Inclinometer 1 and
Inclinometer 2 locations, indicating that the movements
were in response to the activities along State Street. The
slight
inclination observed in both inclinometers on Day 11 is
in response to secant pile installation activities. Between
Days 11 and 81, Inclinometers 1 and 2 respond to the excavation
advancing towards the north. Note that movements between
Day 137 and Day 176 were directed towards the south at
Inclinometer
1 and towards the north at Inclinometer 2. These incremental
movements were caused by excavating the escalator base
slab pit located between the two inclinometers (refer to
Figure
4-1). The direction of movement observed between Day 266
and Day 353 for both inclinometers was in response to the
backfill activities, which proceeded from south to north.
The lateral ground movements at Inclinometer 5 were primarily
oriented towards State Street until day 109 indicating
that the ground movements to this point developed mostly
as a
result of activities along the State Street excavation.
The small component of northward movement between Day 0 and
Day
79 developed as the secant pile wall was installed along
Chicago Avenue. The excavation along State Street was completed
at the Inclinometer 1 location on Day 116. At this time,
the lateral movements began responding more to the north
excavation activities. This resulted in the deformation
vector moving towards the northwest.
4.3.4.3 Comparison of Settlements and Lateral
Movements
Figure
4-22 shows a comparison of lateral movements measured
at Inclinometers 1 and 2 and settlement data for sections
taken perpendicular to the east secant pile wall through
the inclinometer locations. Because the settlement data
represents soil movements at elevation +0.6 m CCD, the
inclinometer data were plotted horizontally by rotating
its axis 90 degrees about this elevation, at the respective
inclinometer locations. Good agreement is observed between
the two data sets at both locations. Slight differences
developed after backfill was completed on Day 355, as a
result of small consolidation settlements arising from
the lowered water table (see Figure 4-10). The agreement
between the settlement behind the excavation support wall
and the lateral movements shows that there was essentially
no volume change in the saturated clays until after the
excavation had reached final grade. The volume changes
that occurred after Day 117 were a consequence of the excavation-induced
drop in the groundwater level. The agreement between the
inclinometer and settlement data suggests that settlement
behind the support wall can be reliably estimated from
inclinometer data when considering excavations through
saturated clay.
This fact is extremely beneficial when designing
an excavation support system to minimize excavation-related
damage to adjacent
structures. Current state-of-the-art procedures use finite
element models to design excavation support systems. Finite
element models used to predict wall deflections provide
relatively good accuracy if a representative soil model is
used and
construction procedures are accurately represented in the
analysis. However, prediction of the ground surface settlement
induced by excavation is not as good as that of the wall
deflection. The finite element models tend to underpredict
the vertical movements at the wall and overpredict the
vertical movements away from the wall (Finno and Harahap,
1991), and
hence any direct predictions of distortions under a building
will not be accurate. However, based on the observations
of the agreement between inclinometer and settlement data,
computed lateral deformations can be used to predict the
settlement distribution behind the support wall, and hence
to predict expected distortions beneath a building. This
approach is valid only for cases involving no volume changes
during excavation, as is typical for excavations through
saturated soft to medium clay.
4.4 LOADS IN CROSS-LOT BRACES AND TIEBACKS
The loads in the struts and tiebacks located
adjacent to the Inclinometer 1 location are given in Figure
4-23. These loads included strain gauge data from Strut
4 and Strut 5 and load cell data from the upper and lower
tiebacks below Inclinometer 1. The loads in the struts and
tiebacks that corresponded to the Inclinometer 2 location
are given in Figure
4-24. These loads included strain gauge data from Strut
3 and Strut 4 and load cell data from the upper and lower
tiebacks below Inclinometer 2. In the figure, the loads are
given in units of force per unit width of the tributary area
of the support. The loads presented for the tiebacks were
obtained dividing the load recorded by the load cell by the
center-to-center spacing of the tiebacks (1.5 m). The loads
per width of wall given for the struts were obtained by dividing
the axial load derived from the strain gauge readings by
the center-to-center spacing of the struts (6.1 m). The axial
loads were calculated by first plotting the observed strains
with respect to their distances from the neutral axis, which
yielded the strain distribution in the strut. To remove the
effects of bending due to self-weight of the strut, the axial
strain at the neutral axis was multiplied by the cross-sectional
area and the modulus of elasticity of the strut to obtain
axial load.
The struts were not preloaded prior to recording
the strain measurements. Consequently, the strut loads begin
at zero
and gradually increased to between 115 kN per m and 130 kN
per m in response to the excavation. The design load for
all struts was 120 kN per m. After the excavation reached
its full depth at both locations (Day 114 at Inclinometer
2 and Day 116 at Inclinometer 1), fluctuations of ± 25
kN per m were observed. The fluctuations observed in the
strut loads are primarily due to fluctuations in the temperature.
The upper and lower level tiebacks on the east side were
locked-off at 220 kN per m and 280 kN per m, respectively.
These lock-off loads were equivalent to 80 percent of the
design loads.
Both Figure 4-23 and Figure 4-24 show that
when the lower level of tiebacks were installed and prestressed,
the loads
in the upper level tiebacks decreased by about 20 kN per
m. During the same time, the loads in the lower tiebacks
increased by a similar amount. Thereafter, the tieback loads
essentially remained constant with variations of no more
than ± 10 kN per m. This response suggests that the
anchors embedded in the stiff to hard clays did not creep
significantly over the 170-day period when data were obtained.
4.5 SUMMARY
The construction at the site was separated
into three stages; wall installation, support system installation
and excavation,
and station renovation and backfill. Lateral soil movements
of the secant pile wall developed as the wall was installed
with the maximum movement occurring within the soft clay.
The lateral movements extended to the depth of the secant
pile wall. The lateral movements associated with stress relief
from the excavation were on average about one-half the total
movement. The significance of this observation is that often
only the movements associated with stress relief during excavation
and support placement are considered when predicting the
movements associated with supported excavations. Some of
the lateral movements were attributed to a reduction in bending
stiffness of the wall, which was the result of chipping the
secant pile walls to the flange of the W24x55 sections for
their entire exposed length.
It was observed that larger lateral
movements occurred at the location of Inclinometer 4 on
the west wall compared
to the locations of Inclinometer 1 and 2 on the east wall.
This was due to the presence of surcharge loads on the
west side, in the form of construction equipment and materials
and the higher insitu stresses in the soil because of the
absence of an overcompensated structure on that side of
the
excavation. The larger movements on the west side were
also a function of the large movements that occurred during
wall
installation.
At the Inclinometer 5 location, the lateral
movements were divided into a north-south component (toward
Chicago Avenue)
and an east-west component (toward State Street). The resultant
of the two components of the lateral movement tracks the
development of the surface settlement much better than
either of the individual components and suggests that the
deformational
behavior of the northwest corner was a function of the
3-D excavation geometry at that location.
It was observed
that Warde School settled as much as the soil displaced laterally,
with the settlement extending as
far behind the excavation as the secant pile wall extended
below the bottom of the school’s foundation. The adjacent
settlements were virtually identical to the lateral movements
within the soft clay until after the excavation was complete
and the secant pile wall had been chipped to the flange.
Thereafter, the settlements became slightly greater than
the maximum lateral movements.
The struts were not preloaded
prior to recording the strain measurements. Consequently,
the strut loads begin at zero
and gradually increased to between 115 kN per m and 130
kN per m in response to the excavation. The tieback anchors
were embedded in the stiff to hard clays. Loads in these
elements essentially held their lock-off loads and did
not
creep significantly over the 170-day period when data were
obtained.
|