APPENDIX A
CONSTRUCTION ACTIVITY, TIME HISTORY AND STRUCTURAL PLAN

Back to Table of Contents

Table A-1. Construction Activities Time History

Date

Day

Activity

6/21/1999

 

Start of Construction

   

Inclinometer and Piezometer Installation

6/10/1999

-11

Inclinometer 1 (74 ft deep)

6/11/1999

-10

Piezometer 1A and 1B (cells @ 33 ft and 43 ft BGS)

6/11/1999

-10

Inclinometer 2A (only 54 ft deep because of squeezing ) + 3 samples

6/14/1999

-7

Inclinometer 4A (74 ft deep) + 1 Sample

6/14/1999

-7

Piezometer 4A and 4B (cells @ 35ft and 45 ft BGS)

6/16/1999

-5

Inclinometer 3 (74 ft deep)

6/17/1999

-4

Inclinometer 2B (74 ft deep)

6/29/1999

8

Inclinometer 5 (74 ft deep)

   

Inclinometer 4 Damage

8/11/1999

51

Inclinometer 4B (80 ft BGS)

10/8/1999

109

Inclinometer 4B Destroyed

10/22/1999

123

Inclinometer 4C (80ft bgs)

   

Piezometer 4 Damage

8/4/1999

44

Piezometer 4 Broken

8/12/1999

52

New Piezometer 4 (4C @ 35ft and 4D @ 45ft BGS)

   

Inclinometer 1 Damage

8/14/1999

54

Inclinometer 1 broken 5 ft BGS

   

Inclinometer 5 Damage

8/25/1999

65

Inclinometer 5 broken

8/27/1999

67

Inclinometer 5B (80 ft BGS)

8/30/1999

70

Inclinometer 5B cut down

9/8/1999

79

Inclinometer 5B read with extension (down to 74')

9/16/1999

87

Inclinometer 5B blown out (back down to 80')

   

Southeast Wall Installation

6/22/1999

1

PILES E2

6/24/1999

3

PILES E1, E3

   

East Wall Installation - South

6/21/1999

0

PILES E4

6/23/1999

2

PILES E6

6/25/1999

4

PILES E5

6/28/1999

7

PILES E7

   

East Wall Installation - INCL 2B

6/21/1999

0

PILES E8

6/22/1999

1

PILES E10, E14, E18

6/23/1999

2

PILES E6, E12, E16

6/25/1999

4

PILES E5, E9, E13

6/26/1999

5

PILES E17

6/28/1999

7

PILES E7, E11

6/29/1999

8

PILES E15

   

East Wall Installation - Central

6/22/1999

1

PILES E22(beg.)

6/23/1999

2

PILES E22(end), E26, E30

6/24/1999

3

PILES E20, E24, E28, E32

6/25/1999

4

PILES E27

6/28/1999

7

PILES E19

6/29/1999

8

PILES E21, E25, E31

6/30/1999

9

PILES E23, E29

   

East Wall Installation - INCL 1

6/23/1999

2

PILES E34, E37

6/24/1999

3

PILES E42

6/25/1999

4

PILES E36, E40

6/28/1999

7

PILES E33, E35

6/29/1999

8

PILES E39

6/30/1999

9

PILES E38, E43

7/2/1999

11

PILES E41

   

East Wall Installation - North 1 (grouped based on dates)

6/24/1999

3

PILES E45

6/25/1999

4

PILES E46

7/2/1999

11

PILES E44

   

East Wall Installation - North 2 (grouped based on dates)

7/14/1999

23

PILES E47

7/17/1999

26

PILES E48, E51

7/19/1999

28

PILES E49

7/21/1999

30

PILES E50

   

Install North Wall - Phase II

8/30/1999

70

PILES E67

8/31/1999

71

PILES E55, E59, E63

9/1/1999

72

PILES E57, E61

9/2/1999

73

PILES E53, E65

9/3/1999

74

PILES E60, E64, E68

9/4/1999

75

PILES E52, E56, E66

9/7/1999

78

PILES E62

9/8/1999

79

PILES E54-E58

   

West Wall Installation - W4

6/21/1999

0

PILES W4

   

Southwest Wall Installation

7/6/1999

15

PILES W2

7/7/1999

16

PILES W1, W3

   

West Wall Installation - South

6/30/1999

9

PILES W7

7/6/1999

15

PILES W6, W8

7/7/1999

16

PILES W5(beg.), W11

7/8/1999

17

PILES W5(end)

7/14/1999

23

PILES W12 (beg.)

7/15/1999

24

PILES W9, W12 (end)

7/17/1999

26

PILES W10

   

West Wall Installation - Drift Tunnel

6/30/1999

9

PILES W13(beg.)*, W15(beg.)*, W19(beg.)*

7/2/1999

11

PILES W17(beg.)*

7/15/1999

24

PILES W14

7/17/1999

26

PILES W15(end)

7/21/1999

30

PILES W13(end), W17(end)

7/23/1999

32

PILES W19(end)

7/26/1999

35

PILES W16

7/27/1999

36

PILES W20

7/28/1999

37

PILES W18

   

West Wall Installation - Central

7/6/1999

15

PILES W23, W25, W27, W31

7/7/1999

16

PILES W21, W24, W26, W29, W32

7/8/1999

17

PILES W22, W28, W30

   

West Wall Installation - INCL 4

7/6/1999

15

PILES W33, W39, W43, W47

7/7/1999

16

PILES W35, W37, W41, W45

7/8/1999

17

PILES W34, W40, W44, W46

7/9/1999

18

PILES W36, W38, W42

   

West Wall Installation - North

7/17/1999

26

PILES W48

7/19/1999

28

PILES W49, W51

7/21/1999

30

PILES W53

7/22/1999

31

PILES W52

7/23/1999

32

PILES W50

   

Drift Tunnel

6/30/1999

9

Drift Tunnel found (W13 thru W19)

7/2/1999

11

Sink Hole in Parking Lot

7/15/1999

24

Beging Concrete Backfill

7/19/1999

28

End Concrete Backfill

   

South Soldier Pile Wall Installation

7/9/1999

18

SOLDIER PILE S1, S2, S3, S6, S7, S8, S9, S10, S11

7/14/1999

23

SOLDIER PILE S4, S5

   

Install Sheet Pile

10/13/1999

114

Installed WF PZ27 sheet pile in northwest corner of the excavation

   

North Soldier Pile Wall Installation

10/19/1999

120

SOLDIER PILE 2-14, 2-15, 2-17, 2-18

10/20/1999

121

SOLDIER PILE 2-13, 2-12, 2-11, 2-10

10/21/1999

122

SOLDIER PILE 2-9, 2-8, 2-7, 2-6, 2-5

10/22/1999

123

SOLDIER PILE 2-19, 2-20, 2-21, 2-4

   

Install Struts - Phase I

8/16/1999

56

STRUT #1

8/18/1999

58

STRUT #2

8/19/1999

59

STRUT #3 (with strain gauges)

8/20/1999

60

STRUT #4 (with strain gauges)

9/3/1999

74

STRUT #5 (with strain gauges)

9/8/1999

79

STRUT #6

   

Remove Struts - Phase I

2/14/2000

238

Cut STRUT #4 and STRUT #5 and relocated adjacent to STRUT #3 and STRUT #6

2/23/2000

247

Removed STRUTS #1 and STRUTS #2

2/25/2000

249

Removed STRUTS #3 and SE corner diagonal bracing

3/5/2000

258

Removed STRUTS #4, STRUT #5, and STRUTS #6

   

Install and Remove Struts - Phase II

10/27/1999

128

1st Level of bracing on North Wall

11/1/1999

133

Installed 1st Level Bracing at the west end of Stair #3

1/13/2000

206

Lower Level Phase II Strut, inclined at the SW corner and bolted to Mezz. floor

2/11/2000

235

Welder cut lower level and upper level Phase II bracing

   

South Soldier Pile Wall Struts and Walers

2/4/2000

228

South Soldier Pile Wall: Removed lower level bracing and waler

   

Waler Installation and Removal - East Wall

7/16/1999

25

Began excavating trench (10ft-wide x 5ft-deep) for east secant pile wall waler

7/20/1999

29

End excavating trench for east secant pile wall waler

7/20/1999

29

Began installing upper-level wale on the east wall and southeast corner bracing

7/24/1999

33

End installing southeast corner bracing

7/23/1999

32

End installing upper-level waler on the east wall

2/26/2000

250

Removed east upper level waler from <M1> to <P7>

3/5/2000

258

Removed remaining east upper level waler

   

Waler Installation and Removal - West Wall

7/29/1999

38

Began excavating trench (9ft-wide x 5ft-deep) for west secant pile wall waler

7/30/1999

39

End excavating trench for west secant pile wall waler

7/29/1999

38

Excavate to 5ft bgs from W6 to W50 for west wall upper waler installation

7/30/1999

39

Installed upper-level waler on the west wall

2/26/2000

250

Removed west upper level waler from <M1> to <P7>

3/5/2000

258

Removed remaining west upper level waler

   

Waler Installation and Removal - North Wall

10/26/1999

127

Installed Waler on North Wall at EL +11.0

2/26/2000

250

Removed Phase II upper level waler

   

Install Sanitary Sewer on West Side

8/3/1999

43

Excavate 12 ft deep trench on west side of west wall for 24in SS (W5 to W30)

8/4/1999

44

Excavate 12 ft deep trench on west side of west wall for 24in SS (W30 to W40)

8/5/1999

45

Excavate 12 ft deep trench on west side of west wall for 24in SS (W40 to W50)

   

Install Sanitary Sewer on East Side

8/12/1999

52

Began install and excavate 12 ft deep trench on east side of east wall for 30in SS DIP

8/17/1999

57

End install and excavate 12 ft deep trench on east side of east wall for 30in SS DIP

   

Install Sanitary Sewer on North Side

8/21/1999

61

Began install and excavate 12 ft deep trench on northwest side of FXW for 30in SS DIP

8/27/1999

67

End install and excavate 12 ft deep trench on northwest side of FXW for 30in SS DIP

11/3/1999

135

Began install and excavate 12 ft deep trench on north side of FXW for 30in SS DIP

11/8/1999

140

End install and excavate 12 ft deep trench on north side of FXW for 30in SS DIP

   

Chipping East Wall

8/17/1999

57

East Wall Chipped (to flange) at 12ft bgs to accommodate 30in SS DIP from E42 to E50

8/20/1999

60

East Wall Chipped (to flange) at el -1.0 from E6 to E22

8/21/1999

61

East Wall Chipped (to flange) to Pile E24

8/23/1999

63

East Wall Chipped (to flange) to Pile E34

8/25/1999

65

East Wall Chipped (inside flange) from Pile E22 to E32 Per revised shop dwg detail

8/26/1999

66

East Wall Chipped (inside flange) from E32 to E34

8/28/1999

68

East Wall Chipped (inside flange) from E34 to E36

9/1/1999

72

East Wall  Chipped (inside flange) from E36 to E37

9/2/1999

73

East Wall  Chipped (inside flange) from E36 to E42

9/7/1999

78

East Wall  Chipped (inside flange) from E42 to E44

9/9/1999

80

East Wall  Chipped (inside flange) from E44 to E46

9/10/1999

81

East Wall  Chipped (inside flange) from E46 to E50

9/13/1999

84

East Wall  Chipped (inside flange) from E46 to E51

9/18/1999

89

East Wall Chipped from E6 to E16 (2nd level)

9/22/1999

93

East Wall Chipped to E40 (2nd level)

9/25/1999

96

East Wall Chipped to E47 (2nd level)

10/2/1999

103

East Wall Chipped to E51 (2nd level)

10/9/1999

110

East Wall Chipped from EL +11.0 to -1.0 from E50 to E32

10/9/1999

110

East Wall Chipped from EL -1.0 to -14.0 from E44 to E34

10/16/1999

117

East Wall Chipped from EL -1.0 to EL -14.0 from E50 to E44

10/16/1999

117

Begin East Wall Chipped from EL -8.0 to EL -12.0 from E34 to E14

10/18/1999

119

End East Wall Chipped from EL -8.0 to EL -12.0 from E34 to E14

10/18/1999

119

Begin East Wall Chipped from EL -8.0 to EL -12.0 from E14 to E7

10/21/1999

122

End East Wall Chipped from EL -8.0 to EL -12.0 from E14 to E7

11/5/1999

137

East Wall Chipped to Flange from EL +11.0 to EL -1.0 from E32 to E26

11/5/1999

137

East Wall Chipped to Flange from EL -1.0 to EL -14.0 from E34 to E7

11/5/1999

137

East Wall Chipped to Flange from EL -14.0 to EL -25.0 from E34 to E17

11/8/1999

140

East Wall Chipped to Flange from EL -14.0 to EL -25.0 from E50 to E42

11/17/1999

149

East Wall Chipped from EL +11.0 to -1.0 from E26 to E17

11/17/1999

149

East Wall Chipped to Flange from EL -14.0 to EL -25.0 from E17 to E12

12/5/1999

167

East Wall Chipped to Flange between UL and LL from E51 to E54

   

Chipping West Wall

8/20/1999

60

West wall Chipped at el -3.0  from W6 to W20 (to flange)

8/23/1999

63

West Wall Chipped from W20 to W26 (inside flange)

8/24/1999

64

West Wall Chipped from W26 to W30 (inside flange)

9/7/1999

78

West Wall Chipped from W30 to W34

9/10/1999

81

West Wall Chipped from W34 to W38

9/13/1999

84

West Wall Chipped from W38 to W42

9/18/1999

89

West Wall Chipped from W42 to W50

9/22/1999

93

West Wall Chipped to W24 (2nd level)

9/25/1999

96

West Wall Chipped to W38 (2nd level)

10/2/1999

103

West Wall Chipped to W46 (2nd level)

10/16/1999

117

West Wall Chipped from EL-8.0 to EL -16.0 from W46 to W14

10/21/1999

122

West Wall Chipped from EL-8.0 to EL -16.0 from W50 to W46

10/29/1999

130

West Wall Chipped from EL+11.0 to EL -1.0 from W50 to W32

10/29/1999

130

West Wall Chipped from EL-1.0 to EL -15.0 from W50 to W32

11/1/1999

133

West Wall Chipped from EL-15.0 to EL -26.0 from W24 to W22

11/1/1999

133

West Wall Chipped from EL+11.0 to EL -1.0 from W32 to W20

11/2/1999

134

West Wall Chipped from EL-15.0 to EL -26.0 from W54 to W34

11/4/1999

136

West Wall Chipped from EL-15.0 to EL -27.0 from W18 to W6

11/5/1999

137

West Wall Chipped to Flange from EL -1.0 to EL -15.0 from W32 to W6

11/5/1999

137

West Wall Chipped to Flange from EL -15.0 to EL -26.0 from W34 to W24

12/2/1999

164

West Wall Minor Chipped to Flange Between UL and LL Tieback Walers from W52 to W26

12/3/1999

165

West Wall Minor Chipped to Flange Between UL and LL Tieback Walers from W26 to W16

   

Chipping North Wall

10/26/1999

127

North Wall Chipped to flange at EL +11.0 from E68 to E55

1/6/2000

199

North Wall Chipped to flange from E68 to E55

1/6/2000

199

Northeast Corner of East Wall Chipped